Major Relief for SEPC as Madras High Court Lifts Attachment on Rs 154 Crore Receivables Following Dispute Settlement
The company says the settlement was funded by another judgment debtor under a 2015 indemnity agreement, with no direct cash outflow for SEPC.
Key Highlights of the Order
- Full and final settlement: The parties agreed to a total settlement of ₹149.5 crore, comprising a Demand Draft of ₹147 crore submitted before the Court and ₹2.5 crore already lying to the credit of the Court, which will be paid to the Award Holders.
- Nil outflow for SEPC: The settlement amount has been paid entirely by another party under a 2015 indemnity agreement, with no direct monetary outflow for the Company.
- ₹154 crore of receivables unlocked: All interim attachments made under these petitions now stand raised, releasing receivables of ₹154 crore with immediate effect.
- Banking operations restored: All restrictions on the Company’s banking operations have been completely lifted with immediate effect.
- All proceedings closed: All listed and un-numbered Execution Petitions have been terminated and all connected pending applications closed.